The 145th st interchange appears to be $7 million over budget. Report seems to be about how important the work done was and is clearly being read aloud. We know it's important, why is it $7 million over budget?
Seems like most of the problem was utility work overages, some of which may be reimbursed by SCL and PSE, etc. Could impact Shoreline by as much as $4.5 million.
Roundabout set to open partially in Sept 25 (west side) and Feb 26 (east side) with full opening in summer of 26, but it is a half-year behind schedule.