The 145th st interchange appears to be $7 million over budget. Report seems to be about how important the work done was and is clearly being read aloud. We know it's important, why is it $7 million over budget?
Comments
Log in with your Bluesky account to leave a comment
Seems like most of the problem was utility work overages, some of which may be reimbursed by SCL and PSE, etc. Could impact Shoreline by as much as $4.5 million.
Roundabout set to open partially in Sept 25 (west side) and Feb 26 (east side) with full opening in summer of 26, but it is a half-year behind schedule.
Comments
CM Scully has concerns about the cost differences in bids like I called out before.
Apparently some of these were due to a pole being 18 inches out of reach. That level of small problem causing delay.